Question 1-  What do you mean by Fe 500D re-bar?

Answer -

Various grades of Re-bars are used in civil engineering works I. e. Construction of structures, buildings etc. 

Some text is written on re-bars(Fe 500D) that provides following information. 

Where (Fe-500D)

Fe- It stand for iron

500- Minimum yield strength

D-  Ductility (Not for diameter)

Question 2- What is DBM? 

 เคช्เคฐเคถ्เคจ 2- เคกीเคฌीเคเคฎ เค•्เคฏा เคนै?

Answer-DBM - The full form of DBM is Dense Bituminous macadam.

DBM is mixture of sand(fine aggregate) , coarse aggregate,filler and bitumen in suitable proportions.

DBM - DBM เค•ा เคชूเคฐ्เคฃ เคฐूเคช Dense Bituminous Macadam เคนै।

 เคกीเคฌीเคเคฎ เค‰เคชเคฏुเค•्เคค เค…เคจुเคชाเคค เคฎें เคฐेเคค(sand), coarse aggregate , เคญเคฐाเคต (filler)  เค”เคฐ เค•ोเคฒเคคाเคฐ(Bitumen) เค•ा เคฎिเคถ्เคฐเคฃ เคนै।

 

To know more about DBM,kindly click on below ๐Ÿ”— 

Dense bituminous macadam(DBM) Specifications as per Indian standard/MORTH

Question 3 -Why dowel bars are used in PQC roads?

เคช्เคฐเคถ्เคจ 3-PQC เคธเคก़เค•ों เคฎें Dowel bar เค•ा เค‰เคชเคฏोเค— เค•्เคฏों เค•िเคฏा เคœाเคคा เคนै?

Answer- Dowel bars are used in pavement quality concrete (PQC)  because these bars(Dowel Bars) transfer load from one slab to another. Dowel bars also allow the horizontal slab movement (Expansion and contraction) which takes place due to Change in temperature and also helps to maintain slab alignment.

 เค‰เคค्เคคเคฐ- เคกॉเคตेเคฒ เคฌाเคฐ เค•ा เค‰เคชเคฏोเค— PQC เคฎें เค•िเคฏा เคœाเคคा เคนै เค•्เคฏोंเค•ि เคฏे เคฌाเคฐ (Dowel bars ) เคเค• เคธ्เคฒैเคฌ เคธे เคฆूเคธเคฐे เคธ्เคฒैเคฌ เคฎें  เคฒोเคก เคŸ्เคฐांเคธเคซเคฐ เค•เคฐเคคे เคนैं।  เคกॉเคตेเคฒ เคฌाเคฐ เค•्เคทैเคคिเคœ เคธ्เคฒैเคฌ movement (เคตिเคธ्เคคाเคฐ เค”เคฐ เคธंเค•ुเคšเคจ) เค•ो เคญी เค…เคจुเคฎเคคि เคฆेเคคा เคนै เคœो เคคाเคชเคฎाเคจ เคฎें เคชเคฐिเคตเคฐ्เคคเคจ เค•े เค•ाเคฐเคฃ เคนोเคคा เคนै เค”เคฐ เคธ्เคฒैเคฌ เคธंเคฐेเค–เคฃ (alignment) เค•ो เคฌเคจाเค เคฐเค–เคจे เคฎें เคญी เคฎเคฆเคฆ เค•เคฐเคคा เคนै।

Question 4 - What is the Difference between WMM(Wet mix macadam) and WBM(Water bound macadam)? 

เคช्เคฐเคถ्เคจ 4 - WMM (เคตेเคŸ เคฎिเค•्เคธ เคฎैเค•เคกैเคฎ) เค”เคฐ WBM (เคตाเคŸเคฐ เคฌाเค‰ंเคก เคฎैเค•เคกैเคฎ) เคฎें เค•्เคฏा เค…ंเคคเคฐ เคนै?

Answer- 

1- WBM stand for Water Bound Macadam. WBM consist of clean crushed aggregates with screening, binding material (Filler) where required. 

While WMM stands for Wet Mix macadam. WMM consist of clean, Crushed ,graded aggregate and granular material.

 เคœเคตाเคฌ- 

1- WBM เค•ा เคชूเคฐ्เคฃ เคฐूเคช เคตॉเคŸเคฐ เคฌाเค‰ंเคก เคฎैเค•เคกैเคฎ (water bound macadam) เคนोเคคा เคนै।  WBM เคฎें เคธ्เค•्เคฐीเคจिंเค—, เคฌाเค‡ंเคกिंเค— เคฎเคŸीเคฐिเคฏเคฒ (เคซिเคฒเคฐ) เค•े เคธाเคฅ เคธाเคซ เค•ुเคšเคฒे เคนुเค เคเค—्เคฐीเค—ेเคŸ(crushed aggregate) เคถाเคฎिเคฒ เคนोเคคे เคนैं, เคœเคนां เค†เคตเคถ्เคฏเค•เคคा เคนोเคคी เคนै।

 เคœเคฌเค•ि WMM เค•ा เคฎเคคเคฒเคฌ เคตेเคŸ เคฎिเค•्เคธ เคฎैเค•เคกैเคฎ (wet mix macadam) เคนोเคคा เคนै।  WMM เคฎें เคธाเคซ, เค•ुเคšเคฒा(crushed) , เค—्เคฐेเคกेเคก เคเค—्เคฐीเค—ेเคŸ เค”เคฐ เค—्เคฐेเคจ्เคฏुเคฒเคฐ เคฎเคŸेเคฐिเคฏเคฒ เคนोเคคा เคนै।

2- Water is postmixed in WBM while in WMM, water is premixed.

 2- WMM เคฎे เคชाเคจी เคชเคนเคฒे เคฎिเคฒाเคฏा เคœाเคคा เคนै เคœเคฌเค•ि WBM เคฎे เคชाเคจी เคฌाเคฆ เคฎे เคฎिเคฒाเคฏा เคœाเคคा เคนै  

3 -The maximum aggregate size used in WBM mix is 75 mm while in WMM, Maximum Aggregate size is 53 mm. 

3-WBM เคฎिเคถ्เคฐเคฃ เคฎें เค‰เคชเคฏोเค— เค•िเค เคœाเคจे เคตाเคฒे เค…เคงिเค•เคคเคฎ aggregate เค•ा เค†เค•ाเคฐ 75 เคฎिเคฎी เคนै เคœเคฌเค•ि WMM เคฎें, เค…เคงिเค•เคคเคฎ aggregate เค•ा เค†เค•ाเคฐ 53 เคฎिเคฎी เคนै।

4 - After final compaction of WBM, The pavement shall be allowed to dry overnight and in next morning, Hungry spots shall be filled with screening and binder material  I.e aggregate, screening and binder material layers are laid one after another.

While in WMM, aggregate and granular materials are pre- mixed in bins of batching Plant. 

 4 - เคกเคฌ्เคฒ्เคฏूเคฌीเคเคฎ เค•े เค…ंเคคिเคฎ เคธंเค˜เคจเคจ เค•े เคฌाเคฆ, เคซुเคŸเคชाเคฅ เค•ो เคฐाเคค เคญเคฐ เคธूเค–เคจे เคฆिเคฏा เคœाเคเค—ा เค”เคฐ เค…เค—เคฒी เคธुเคฌเคน, เคญूเค–े เคธ्เคฅाเคจों เค•ो เคธ्เค•्เคฐीเคจिंเค— เค”เคฐ เคฌांเคงเคจे เค•ी เคธाเคฎเค—्เคฐी เคธे เคญเคฐा เคœाเคเค—ा। เค•ुเคฒ เคฎिเคฒाเค•เคฐ, เคธ्เค•्เคฐीเคจिंเค— เค”เคฐ เคฌाเค‡ंเคกเคฐ เคธाเคฎเค—्เคฐी เค•ी เคชเคฐเคคें เคเค• เค•े เคฌाเคฆ เคเค• เคฐเค–ी เค—เคˆ เคนैं।

 WMM เคฎें, เค•ुเคฒ เค”เคฐ เคฆाเคจेเคฆाเคฐ เคธाเคฎเค—्เคฐी เคฌैเคšिंเค— เคช्เคฒांเคŸ เค•े เคกिเคฌ्เคฌे เคฎें เคชूเคฐ्เคต เคฎिเคถ्เคฐिเคค เคนोเคคी เคนै।

5- Quantity of water used is less in WMM as compared to WBM. 

 5- WBM เค•ी เคคुเคฒเคจा เคฎें WMM เคฎें เค‰เคชเคฏोเค— เค•िเค เค—เค เคชाเคจी เค•ी เคฎाเคค्เคฐा เค•เคฎ  เคนोเคคी เคนै।

6 - WBM coarses take more time in construction as compared to WMM. 

6 - WBM เค•े เคจिเคฐ्เคฎाเคฃ เคฎें  WMM เค•ी เคคुเคฒเคจा เคฎें เคฒเค—เคคा เค…เคงिเค• เคธเคฎเคฏ เคนै।

To get the more information about wet mix macadam (WMM), please click on below ๐Ÿ”— 

wet-mix-macadam(WMM) specifications as per Indian standard/MORTH



Question 5 - What is the Difference between Prime coat and Tack coat ? 

เคช्เคฐเคถ्เคจ 5 - เคช्เคฐाเค‡เคฎ เค•ोเคŸ (Prime coat) เค”เคฐ เคŸैเค• เค•ोเคŸ (tack coat) เคฎें เค•्เคฏा เค…ंเคคเคฐ เคนै?

Answer- 

1 - Prime coat is applied on base course(At WMM course or WBM coarse) While tack coat is applied on surface treated with prime coat, bituminous base course (on the surface of DBM before laying Bituminous Concrete) and Concrete surface(Before laying bituminous layer over concrete surface).

 1 - เคช्เคฐाเค‡เคฎ เค•ोเคŸ, เคฌेเคธ เค•ोเคฐ्เคธ (WMM and WBM coarse เคชเคฐ) เคชเคฐ เคกाเคฒा เคœाเคคा เคนै เคœเคฌเค•ि tack coat , Prime coat , เคฌिเคŸुเคฎिเคจเคธ เคฌेเคธ เค•ोเคฐ्เคธ (เคฌिเคŸुเคฎिเคจเคธ เค•ंเค•्เคฐीเคŸ เคฌिเค›ाเคจे เคธे เคชเคนเคฒे เคกीเคฌीเคเคฎ เค•ी เคธเคคเคน เคชเคฐ) เค”เคฐ เค•ंเค•्เคฐीเคŸ เค•ी เคธเคคเคน (เค ोเคธ เคธเคคเคน เคชเคฐ เคชเคฐเคค เคฌिเคŸुเคฎिเคจ เคฌिเค›ाเคจे เคธे เคชเคนเคฒे)  เคชเคฐ เคฒเค—ाเคฏा เคœाเคคा เคนै|

2 - Material used in Prime coat is cationic bitumen emulsion (SS-1) or medium curing cutback bitumen while material used in tack coat is cationic bitumen emulsion (RS-1), Low viscosity paving bitumen of VG 10 grade and for sites at sub- zero temperatures ,cutback bitumen RC:70 is used to apply tack coat.

2 - เคช्เคฐाเค‡เคฎ เค•ोเคŸ เคฎें เค‰เคชเคฏोเค— เค•ी เคœाเคจे เคตाเคฒी เคธाเคฎเค—्เคฐी cationic เค•ोเคฒเคคाเคฐ เค‡เคฎเคฒ्เคถเคจ (SS-1) เคฏा medium curing cutback เค•ोเคฒเคคाเคฐ เคนै, เคœเคฌเค•ि tack เค•ोเคŸ เคฎें เค‰เคชเคฏोเค— เค•ी เคœाเคจे เคตाเคฒी เคธाเคฎเค—्เคฐी cationic เค•ोเคฒเคคाเคฐ เค‡เคฎเคฒ्เคถเคจ (RS-1) เคนै, VG 10 เค—्เคฐेเคก เค•ी low viscosity เคฌिเคŸुเคฎेเคจ เค”เคฐ เคธाเค‡เคŸ्เคธ เค•े เคฒिเค sub zero เคคाเคชเคฎाเคจ เคชเคฐ -, เค•เคŸเคฌैเค• เคฌिเคŸुเคฎेเคจ RC: 70 เค•ा เค‰เคชเคฏोเค— tack เค•ोเคŸ เคฒเค—ाเคจे เค•े เคฒिเค เค•िเคฏा เคœाเคคा เคนै।

3 - Tack coat is less dense than prime coat .

 3 - เคŸैเค• เค•ोเคŸ เคช्เคฐाเค‡เคฎ เค•ोเคŸ เค•ी เคคुเคฒเคจा เคฎें เค•เคฎ เค˜เคจा เคนोเคคा เคนै।

Question 6- What is the Minimum and maximum Single compacted layer thickness of subgrade,  GSB Layer, WMM Layer, DBM layer and BC layer ? 
เคช्เคฐเคถ्เคจ 6- sub grade, GSB เคฒेเคฏเคฐ, WMM เคฒेเคฏเคฐ, DBM เคฒेเคฏเคฐ เค”เคฐ BC เคฒेเคฏเคฐ เค•ी เคจ्เคฏूเคจเคคเคฎ เค”เคฐ เค…เคงिเค•เคคเคฎ เคธिंเค—เคฒ เค•ॉเคฎ्เคชैเค•्เคŸ เคฒेเคฏเคฐ เคฎोเคŸाเคˆ เค•्เคฏा เคนै?

Answer- 
1 - sub grade 
a) Minimum single compacted layer thickness - 
Not specified (But 75 mm can be considered as minimum single compacted soil layer thickness with 50 mm maximum size of coarse material)

(b) Maximun single compacted layer thickness- 250 mm

2 - GSB layer
(a) Minimum single compacted layer thickness - 150 mm (But sometime it was seen that GSB Layer is laid of 100 mm thickness)

(b) Maximun single compacted layer thickness- 200 mm

3- WMM layer
(a) Minimum single compacted layer thickness - 75 mm
(b) Maximun single compacted layer thickness- 200 mm

4 - DBM layer
(a) Minimum single compacted layer thickness - 50 mm
(b) Maximun single compacted layer thickness- 100 mm

5 - BC layer
(a) Minimum single compacted layer thickness - 30 mm
(b) Maximun single compacted layer thickness - 50 mm

เค‰เคค्เคคเคฐ-
 1 - เคธเคฌ- เค—्เคฐेเคก
 a ) เคจ्เคฏूเคจเคคเคฎ เคเค•เคฒ เคธंเค•ुเคšिเคค เคชเคฐเคค เค•ी เคฎोเคŸाเคˆ -
 เคจिเคฐ्เคฆिเคท्เคŸ เคจเคนीं (เคฒेเค•िเคจ 75 เคฎिเคฎी เค•ो เคฎोเคŸे เคเค•เคฒ เคฎिเคŸ्เคŸी เค•ी เคชเคฐเคค เค•ी เคฎोเคŸाเคˆ เคฎाเคจा เคœा เคธเค•เคคा เคนै เคœिเคธเคฎें 50 เคฎिเคฎी เคฎोเคŸे เค†เค•ाเคฐ เค•े coarse aggregate เคนोเคคे เคนैं)
 (b) เค…เคงिเค•เคคเคฎ เคเค•เคฒ เค•ॉเคฎ्เคชैเค•्เคŸ เคฒेเคฏเคฐ เค•ी เคฎोเคŸाเคˆ- 250 เคฎिเคฎी

 2 - เคœीเคเคธเคฌी เคชเคฐเคค
 (a) เคจ्เคฏूเคจเคคเคฎ เคเค•เคฒ เค•ॉเคฎ्เคชैเค•्เคŸ เคชเคฐเคค เค•ी เคฎोเคŸाเคˆ - 150 เคฎिเคฎी (เคฒेเค•िเคจ เค•เคญी-เค•เคญी เคฏเคน เคฆेเค–ा เค—เคฏा เคฅा เค•ि เคœीเคเคธเคฌी เคชเคฐเคค 100 เคฎिเคฎी เคฎोเคŸाเคˆ เคธे เคฌเคจा เคนै)
 (b) เค…เคงिเค•เคคเคฎ  เคเค•เคฒ เค•ॉเคฎ्เคชैเค•्เคŸ เคฒेเคฏเคฐ เค•ी เคฎोเคŸाเคˆ- 200 เคฎिเคฎी

 3- WMM เคชเคฐเคค
 (a) เคจ्เคฏूเคจเคคเคฎ เคเค•เคฒ เค•ॉเคฎ्เคชैเค•्เคŸ เคชเคฐเคค เค•ी เคฎोเคŸाเคˆ - 75 เคฎिเคฎी
 (b) เค…เคงिเค•เคคเคฎ เคเค•เคฒ เค•ॉเคฎ्เคชैเค•्เคŸ เคฒेเคฏเคฐ เค•ी เคฎोเคŸाเคˆ- 200 เคฎिเคฎी

 4 - DBM เคชเคฐเคค
 (a) เคจ्เคฏूเคจเคคเคฎ เคเค•เคฒ เค•ॉเคฎ्เคชैเค•्เคŸ เคชเคฐเคค เค•ी เคฎोเคŸाเคˆ - 50 เคฎिเคฎी
 (b) เค…เคงिเค•เคคเคฎ เคเค•เคฒ เค•ॉเคฎ्เคชैเค•्เคŸ เคฒेเคฏเคฐ เค•ी เคฎोเคŸाเคˆ- 100 เคฎिเคฎी

 5 - BC เคชเคฐเคค
 (a) เคจ्เคฏूเคจเคคเคฎ เคเค•เคฒ เค•ॉเคฎ्เคชैเค•्เคŸ เคชเคฐเคค เค•ी เคฎोเคŸाเคˆ - 30 เคฎिเคฎी
 (b) เค…เคงिเค•เคคเคฎ เคเค•เคฒ เค•ॉเคฎ्เคชैเค•्เคŸ เคชเคฐเคค เค•ी เคฎोเคŸाเคˆ - 50 เคฎिเคฎी

Question 7 - Why tie bars are used in pavement quality concrete (PQC) pavement?

เคซुเคŸเคชाเคฅ เค—ुเคฃเคตเคค्เคคा เค•ंเค•्เคฐीเคŸ (PQC) เคซुเคŸเคชाเคฅ เคฎें เคŸाเคˆ เคฌाเคฐ เค•ा เค‰เคชเคฏोเค— เค•्เคฏों เค•िเคฏा เคœाเคคा เคนै?

Answer -
Tie bars are generally used at longitudinal joints and edge joint. These bars are generally high yield strength deformation (HYSD) bars. 

Tie bars are used to maintain the faces of rigid pavement slab in position and these bars also transfer the some amount of load but these bars can not be used as main bars for load transfer from one slab to another.

เคŸाเคˆ เคฌाเคฐ เค•ा เค‰เคชเคฏोเค— เค†เคฎ เคคौเคฐ เคชเคฐ เค…เคจुเคฆैเคฐ्เคง्เคฏ เคœोเคก़ों เค”เคฐ เค•िเคจाเคฐे เค•े เคœोเคก़ เคชเคฐ เค•िเคฏा เคœाเคคा เคนै।  เคฏे bars เค†เคฎ เคคौเคฐ เคชเคฐ  high yield strength deformation (HYSD) bars เคนोเคคे เคนैं।

 เคŸाเคˆ bars เค•ा เค‰เคชเคฏोเค— เค•เค ोเคฐ เคซुเคŸเคชाเคฅ เคธ्เคฒैเคฌ เค•े faces เค•ो เคธ्เคฅिเคคि เคฌเคจाเค เคฐเค–เคจे เค•े เคฒिเค เค•िเคฏा เคœाเคคा เคนै เค”เคฐ เคฏे bars เคฒोเคก เค•ी เค•ुเค› เคฐाเคถि เค•ो เคญी เคนเคธ्เคคांเคคเคฐिเคค(transfer) เค•เคฐเคคी เคนैं เคฒेเค•िเคจ เค‡เคจ bars เค•ो เคฎुเค–्เคฏ bars เค•े เคฐूเคช เคฎे เคเค• เคธ्เคฒैเคฌ เคธे เคฆूเคธเคฐे เคธ्เคฒैเคฌ เคชเคฐ เคฒोเคก เค•ो เคนเคธ्เคคांเคคเคฐिเคค เค•เคฐเคจे เคฒिเค เค•े เคฒिเคฏे เค‡เคธ्เคคेเคฎाเคฒ เคจเคนीं เค•िเคฏा เคœा เคธเค•เคคा เคนै।

Question 8 - Why do you Mean by nominal size of aggregate?

Aggregates เค•े nominal (เคจाเคฎเคฎाเคค्เคฐ ) เค†เค•ाเคฐ เคธे เค†เคช เค•्เคฏा เคธเคฎเคเคคे เคนैं?

Answer -
Nominal size of aggregates refers to the that Sieve size (sieve opening) through which 90 -100% of aggregates passes from that sieve size. It means 90 -100% aggregates are smaller than nominal size. 

Aggregates เค•ा nominal เค†เค•ाเคฐ เค‰เคธ เค›เคฒเคจी เค†เค•ाเคฐ (เคšเคฒเคจी เค–ोเคฒเคจा) เค•ो เคธंเคฆเคฐ्เคญिเคค เค•เคฐเคคा เคนै เคœिเคธเค•े เคฎाเคง्เคฏเคฎ เคธे 90 -100% aggregates เค‰เคธ เค›เคฒเคจी เค•े เค†เค•ाเคฐ เคธे เค—ुเคœเคฐเคคे เคนैं।  เค‡เคธเค•ा เคฎเคคเคฒเคฌ เคนै เค•ि 90 -100% aggregates nominal เค†เค•ाเคฐ เคธे เค›ोเคŸे เคนोเคคे เคนैं।

For example - if nominal size for any composition is 19 mm it means 90 -100% aggregates of that composition are small than 19 mm or 90 -100% aggregates will pass through 19 mm sieve opening.

เคฏเคฆि เค•िเคธी เคฐเคšเคจा(composition) เค•े เคฒिเค nominal เค†เค•ाเคฐ 19 เคฎिเคฎी เคนै เคคो เค‡เคธเค•ा เคฎเคคเคฒเคฌ เคนै เค•ि เค‰เคธ เคฐเคšเคจा เค•े 90 -100% aggregates 19 เคฎिเคฎी เคธे เค›ोเคŸे เคนैं เคฏा 90 -100% aggregates 19 เคฎिเคฎी เค•ी เค›เคฒเคจी เค•ी openings เคธे เค—ुเคœเคฐेเค—े।


Question 9 - What do you know about the Reinforced soil earth wall (RS wall / RE Wall) ?

Answer -
• Minimum thickness of RS/RE wall panels is 180 mm. (including facia textures, logos and embellishments)
•Minimum Concrete grade of RS/RE panels is M 35.
• Minimum width of geotextile strip to cover gaps between panels is 100 mm. 
•Height of point of impact at crash barriers above top of pavement is 800 mm. 
•Maximum spacing of reinforcing elements shall not exceed 800 mm for RS/RE wall using panels and blocks. 
•Minimum thickness of strip footing ( levelling pad PCC) is 150 mm. 
•Minimum width of strip footing ( levelling pad PCC) is 350 mm. 
•Minimum concrete grade for levelling pad PCC( strip footing) is M 15.
•Minimum depth of embedment below finished ground level at the foot of wall is 1000 mm. 
•Maximum compacted soil thickness of each layer is 200 mm. 
•Various types of reinforcements used in RS/RE wall
1 - Metallic elements like bars, strips, plates etc. 
2 - Metallic reinforcement in form of mesh
3 - Polymeric elements like strips, grids, rods mesh etc. 
•Minimum length of reinforcement shall be 0.7 H to 3 met. Whichever is greater.
Where H is design height (depth of embedment plus height above ground level) of the RS/RE wall. 

To know more ........click on below ๐Ÿ”— 


Question 10 - When will the berm provide in RE/RS wall? And what shall be the minimum width of such berm? 

RE /RS เคฆीเคตाเคฐ เคฎें เคฌเคฐ्เคฎ (berm) เค•เคฌ เคช्เคฐเคฆाเคจ เค•เคฐेเค—ा?  เค”เคฐ เค‡เคธ เคคเคฐเคน เค•े เคฌเคฐเคฎ เค•ी เคจ्เคฏूเคจเคคเคฎ เคšौเคก़ाเคˆ เค•्เคฏा เคนोเค—ी?

Answer -
Where the height of reinforced soil earth wall exceeds 10 m, the designer may consider providing a berm. And the minimum width of such berm shall be 1.5 m. 

เค‰เคค्เคคเคฐ -
 เคœเคนां เคช्เคฐเคฌเคฒिเคค เคฎिเคŸ्เคŸी เคชृเคฅ्เคตी เค•ी เคฆीเคตाเคฐ(RE/RS wall)  เค•ी เคŠंเคšाเคˆ 10 เคฎीเคŸเคฐ เคธे เค…เคงिเค• เคนो, เคคเคฌ เคกिเคœाเค‡เคจเคฐ เคเค• เคฌเคฐ्เคฎ เคช्เคฐเคฆाเคจ เค•เคฐเคจे เคชเคฐ เคตिเคšाเคฐ เค•เคฐ เคธเค•เคคे เคนैं।  เค”เคฐ เคเคธे  เคฌเคฐ्เคฎ (berm) เค•ी เคจ्เคฏूเคจเคคเคฎ เคšौเคก़ाเคˆ 1.5 เคฎीเคŸเคฐ เคนोเค—ी।

Question 11 - What is the difference between MDD and FDD? 

MDD เค”เคฐ FDD เคฎें เค•्เคฏा เค…ंเคคเคฐ เคนै?

Answer -
MDD - MDD refers to Maximum Dry Density. 
MDD for subgrade,sub base and base course refers to the maximum compaction of layer particles at optimum moisture content(OMC)  by conducting proctor test. and MDD for surface course is also calculated by conducting proctor test. 
MDD is calculated in Laboratory.

FDD - FDD refers to field dry density. 
FDD for subgrade, sub-base course ,base course and surface course means the compaction of layer particles achieved at construction site with the help of Roller or any other compaction equipment.
FDD is always calculated as a percentage measure with respect to MDD. 

เค‰เคค्เคคเคฐ -
 MDD - MDD เค…เคงिเค•เคคเคฎ เคถुเคท्เค• เค˜เคจเคค्เคต เค•ो เคธंเคฆเคฐ्เคญिเคค เค•เคฐเคคा เคนै।
 เคธเคฌเค—्เคฐेเคก, เคธเคฌ เคฌेเคธ เค”เคฐ เคฌेเคธ เค•ोเคฐ्เคธ เค•े เคฒिเค เคเคฎเคกीเคกी เคช्เคฐॉเค•्เคŸเคฐ เคŸेเคธ्เคŸ เค†เคฏोเคœिเคค เค•เคฐเค•े เค‡เคท्เคŸเคคเคฎ เคจเคฎी เคธाเคฎเค—्เคฐी (OMC) เคฎें เคชเคฐเคค เค•เคฃों เค•े เค…เคงिเค•เคคเคฎ เคธंเค˜เคจเคจ เค•ो เคธंเคฆเคฐ्เคญिเคค เค•เคฐเคคा เคนै।  เคช्เคฐॉเค•्เคŸเคฐ เคŸेเคธ्เคŸ เค†เคฏोเคœिเคค เค•เคฐเค•े เคธเคคเคน  เค•े เคฒिเค เคเคฎเคกीเคกी เค•ी เคญी เค—เคฃเคจा เค•ी เคœाเคคी เคนै |MDD เค•ी เค—เคฃเคจा เคช्เคฐเคฏोเค—เคถाเคฒा เคฎें เค•ी เคœाเคคी เคนै।

 FDD - FDD เคถुเคท्เค• เค˜เคจเคค्เคต เค•्เคทेเคค्เคฐ เค•ो เคธंเคฆเคฐ्เคญिเคค เค•เคฐเคคा เคนै।
 Sub grade , เคธเคฌ-เคฌेเคธ เค•ोเคฐ्เคธ, เคฌेเคธ เค•ोเคฐ्เคธ เค”เคฐ เคธเคฐเคซेเคธ เค•ोเคฐ्เคธ เค•े เคฒिเค เคเคซเคกीเคกी เค•ा เคฎเคคเคฒเคฌ เคนै เค•ि เคฐोเคฒเคฐ เคฏा เค•िเคธी เค…เคจ्เคฏ เค•ंเคชเคŸीเคถเคจ เค‰เคชเค•เคฐเคฃ เค•ी เคฎเคฆเคฆ เคธे เคจिเคฐ्เคฎाเคฃ เคธ्เคฅเคฒ เคชเคฐ เคช्เคฐाเคช्เคค เคชเคฐเคค เค•े เค•เคฃों เค•ा เคธंเค˜เคจเคจ।
 เคเคซเคกीเคกी เค•ी เค—เคฃเคจा เคนเคฎेเคถा เคเคฎเคกीเคกी เค•े เคธंเคฌंเคง เคฎें เคช्เคฐเคคिเคถเคค เคฎाเคช เค•े เคฐूเคช เคฎें เค•ी เคœाเคคी เคนै।

Question 12 - What is the minimum width of geotextile strip to cover gaps between panels in the construction of Reinforced soil earth wall ?

 เคช्เคฐเคฌเคฒिเคค เคฎिเคŸ्เคŸी เคชृเคฅ्เคตी เค•ी เคฆीเคตाเคฐ เค•े เคจिเคฐ्เคฎाเคฃ เคฎें เคชैเคจเคฒ เค•े เคฌीเคš เค…ंเคคเคฐाเคฒ เค•ो เค•เคตเคฐ เค•เคฐเคจे เค•े เคฒिเค เคญू เคŸेเค•्เคธเคŸाเค‡เคฒ เคชเคŸ्เคŸी เค•ी เคจ्เคฏूเคจเคคเคฎ เคšौเคก़ाเคˆ เค•्เคฏा เคนै?

Answer -
The Minimum width of geotextile strip to cover gaps between panels is 100 mm. 

เค‰เคค्เคคเคฐ -
 เคชैเคจเคฒ เค•े เคฌीเคš เค…ंเคคเคฐाเคฒ เค•ो เค•เคตเคฐ เค•เคฐเคจे เค•े เคฒिเค เคญू เคŸेเค•्เคธเคŸाเค‡เคฒ เคชเคŸ्เคŸी เค•ी เคจ्เคฏूเคจเคคเคฎ เคšौเคก़ाเคˆ 100 เคฎिเคฎी เคนै।

Question 13 - What is the difference between Retaining wall and Reinforced soil earth wall(RE/RS) Wall? 

Answer -
 Retaining wall - Retaining wall is a rigid structure. These are constructed to bear the lateral pressure of backfill material or soil. 
A huge quantity of reinforcement is used in construction of various parts of Retaining wall like raft(including both Heel portion and toe portion)  and stem. 
Whole lateral pressure is counteracted by stem and raft. 

Reinforced soil earth wall - RS/RE Wall (Reinforced soil earth wall) is a self stabilized and rigid structure that is designed or used to restrain the soil deformation and achieve the desired soil slope.
The stability of RS/RE wall is maintained by its own weight.
The friction between reinforcement (metallic elements or polymeric elements) and soil keeps the structure in its position. Due to this friction force ,less lateral force exerts on precast panel members of RS/RE wall. 

Question 14 - why CBR test is conducted in construction of Highways?  

Answer - CBR stands for California Bearing Ratio. CBR test is conducted to calculate the  strength or bearing capacity of soil. The thickness of pavements and  thickness of layers in road construction are calculated on the the basis of CBR value and curve. 

Question 15 -What is Rolling  and why rolling is required in road construction? 

Answer - Rolling is an artificial process to achieve compaction by pressing the particles close to each other in any required road layers.

Air during Rolling is expelled from the void space in the soil mass and, therefore, the mass density is increased.
Rolling of a soil mass is done to improve its engineering properties.

เคฐोเคฒिंเค— เค•िเคธी เคญी เค†เคตเคถ्เคฏเค• เคธเคก़เค• เคชเคฐเคคों เคฎें เค•เคฃों เค•ो เคเค• เคฆूเคธเคฐे เค•े เค•เคฐीเคฌ เคฆเคฌाเค•เคฐ เคธंเค˜เคจเคจ เคช्เคฐाเคช्เคค เค•เคฐเคจे เค•ी เคเค• เค•ृเคค्เคฐिเคฎ เคช्เคฐเค•्เคฐिเคฏा เคนै

 เคฐोเคฒिंเค— เค•े เคฆौเคฐाเคจ เคนเคตा เค•ो เคฎिเคŸ्เคŸी เค•े เคฆ्เคฐเคต्เคฏเคฎाเคจ(soil mass) เคฎें เคถूเคจ्เคฏ เคธ्เคฅाเคจ(void space) เคธे เคจिเคท्เค•ाเคธिเคค(expelled) เค•เคฐ เคฆिเคฏा เคœाเคคा เคนै เค”เคฐ เค‡เคธเคฒिเค, เคœเคจ ​​เค˜เคจเคค्เคต (mass density) เคฎें เคตृเคฆ्เคงि เคนोเคคी เคนै।
 เคฎिเคŸ्เคŸी เค•े เคฆ्เคฐเคต्เคฏเคฎाเคจ (soil mass) เค•ा เคฐोเคฒिंเค— เค‡เคธเค•े เค‡ंเคœीเคจिเคฏเคฐिंเค— เค—ुเคฃों เค•ो เคฌेเคนเคคเคฐ เคฌเคจाเคจे เค•े เคฒिเค เค•िเคฏा เคœाเคคा เคนै।

To get more information about rolling patterns and number of required passes, kindly click on below link 


Question 16 -What is the maximum depth of soil excavation from borrow area? 

Answer - The maximum depth of soil excavation from borrow area is 1.5 met. 


Question 17 How much % of compaction(FDD) is required for the embankment layer In the construction of road? And What will be the FDD (compaction ) value of embankment layer for more and equal to  6 met. embankment filling  in the Construction of road? 

Answer -Minimum value of FDD for embankment layer is considered as 95 % of MDD. While Minimum value of FDD for embankment layer having  filling height more  or equal to 6 met. should be 97% of MDD.

Question 18 -What is the initial settling time and final settling time of cement? 

Answer - 
(a) Initial setting time: Not less than 30 minutes 
(b) Final setting time: Not more than 600 minutes 

Question 19 -Why is white colour used  instead of yellow colour in road marking on the Concrete surfaces ? 

เค•ंเค•्เคฐीเคŸ เคธเคคเคนों เคชเคฐ เคธเคก़เค• เค•े เค…ंเค•เคจ เคฎें เคชीเคฒे เคฐंเค— เค•े เคฌเคœाเคฏ เคธเคซेเคฆ เคฐंเค— เค•ा เค‰เคชเคฏोเค— เค•्เคฏों เค•िเคฏा เคœाเคคा เคนै?


Answer - Under natural light, the white light reflects the light of most wave-length whereas other colours absorb different wave length of light energy. The yellow colour may offer slightly better contrast with concrete surface compared to white colour. But the reflectivity of white is better as compared to yellow. Moreover, the importance of reflectivity is more during night time and wet conditions. 

 In view of better retro reflectivity and to have uniformity, it has been decided that white colour markings shall be used on concrete surface instead of yellow markings as per IRC:35- 2015.

Question 20 -what do you mean by Bypass, new alignment and realignment of highway? 

เคช्เคฐเคถ्เคจ 20-  เคนाเคˆ-เคตे เค•े เคฌाเคˆเคชाเคธ, เคจเค เคเคฒाเค‡เคจเคฎेंเคŸ เค”เคฐ เคฐीเคเคฒाเค‡เคจเคฎेंเคŸ เคธे เค†เคชเค•ा เค•्เคฏा เค…เคญिเคช्เคฐाเคฏ เคนै?

Answer

1-Bypass road- A new constructed highway to pass the traffic from outer of any city or town is know as bypass road. The Bypasses are constructed to bypass the traffic from outer of city to minimize traffic flow. 

1-By pass road - เค•िเคธी เคญी เคถเคนเคฐ เคฏा เค•เคธ्เคฌे เค•े เคฌाเคนเคฐी เคนिเคธ्เคธे เคธे เคŸ्เคฐैเคซिเค• เค•ो เคชाเคธ เค•เคฐเคจे เค•े เคฒिเค เคเค• เคจเคฏा เคจिเคฐ्เคฎिเคค เคนाเคˆเคตे เคฌाเคˆเคชाเคธ เคฐोเคก เค•े เคฐूเคช เคฎें เคœाเคจा เคœाเคคा เคนै।  เคฏाเคคाเคฏाเคค เค•े เคช्เคฐเคตाเคน เค•ो เค•เคฎ เค•เคฐเคจे เค•े เคฒिเค เคฌाเค‡เคชाเคธ เค•ा เคจिเคฐ्เคฎाเคฃ เคถเคนเคฐ เค•े เคฌाเคนเคฐी เค‡เคฒाเค•ों เคธे เคฏाเคคाเคฏाเคค เค•ो เคจिเค•ाเคฒเคจे  เค•े เคฒिเค เค•िเคฏा เคœाเคคा เคนै।

2- New alignment - when a road is constructed at the location where there was no road exist before it. Such type of road alignment is known as new alignment. 

2- New alignment - เคœเคฌ เค•िเคธी เคธเคก़เค• เค•ा เคจिเคฐ्เคฎाเคฃ เค‰เคธ เคธ्เคฅाเคจ เคชเคฐ เค•िเคฏा เคœाเคคा เคนै เคœเคนाँ เคชเคนเคฒे เค•ोเคˆ เคธเคก़เค• เคฎौเคœूเคฆ เคจเคนीं เคฅी।  เค‡เคธ เคคเคฐเคน เค•े เคธเคก़เค• เคธंเคฐेเค–เคฃ เค•ो เคจเค เคธंเคฐेเค–เคฃ เค•े เคฐूเคช เคฎें เคœाเคจा เคœाเคคा เคนै।

3-Realignment - when a road is constructed by changing its center line (C. L.) at the same location where there was road exist before it.Such type of road alignment is known as Re-alignment of road. And when realignment takes place in whole road project,that project is known as realignment project. 

3-Realignment - เคœเคฌ เค•िเคธी เคธเคก़เค• เค•ो เค‰เคธเค•ी เค•ेंเคฆ्เคฐ เคฐेเค–ा (C. L.) เคธे เคฌเคฆเคฒเค•เคฐ เค‰เคธी เคธ्เคฅाเคจ เคจเคฏी เค•ेंเคฆ्เคฐ เคฐेเค–ा เคชเคฐ เคฌเคจाเคฏा เคœाเคคा เคนै, เคœเคนाँ เคชเคฐ เค‰เคธเค•े เคชเคนเคฒे เคธเคก़เค• เคฎौเคœूเคฆ เคฅी। เคธเคก़เค• เค•े เค‡เคธ เคช्เคฐเค•ाเคฐ เค•े เคจिเคฐ्เคฎाเคฃ เค•ो เคธเคก़เค• เค•े เคชुเคจ: เคธंเคฐेเค–เคฃ เค•े เคฐूเคช เคฎें เคœाเคจा เคœाเคคा เคนै।  เค”เคฐ เคœเคฌ realignment เคชूเคฐे เคฐोเคก เคช्เคฐोเคœेเค•्เคŸ เคฎें เคนोเคคा เคนै, เคคो เค‰เคธ เคช्เคฐोเคœेเค•्เคŸ เค•ो realignment เคช्เคฐोเคœेเค•्เคŸ เค•े เคฐूเคช เคฎें เคœाเคจा เคœाเคคा เคนै।

Question 21 -  What is the difference between W- Beam type crash barriers and Thrie beam type crash barriers? 
W- Beam เคŸाเค‡เคช เค•्เคฐैเคถ เคฌैเคฐिเคฏเคฐ เค”เคฐ Thrie เคฌीเคฎ เคŸाเค‡เคช เค•्เคฐैเคถ เคฌैเคฐिเคฏเคฐ เคฎें เค•्เคฏा เค…ंเคคเคฐ เคนै?

Answer -
1- W - Beam type steel crash barriers 
 it consists of a steel post and a 3 mm thick W - beam rail element attached to a steel block, which in turn is attached to the steel post. The Barrier is of a semi-rigid type. The steel post and the blocked-out spacer are channel section 75 mm x 150 mm size 5 mm thick. 
The rail shall be 700 mm above the ground and 1100 mm below the ground, and shall be spaced at 2 met. centre to centre. The posts, beam, spacer and fasteners shall be galvanised by the hot dip process. 

2 - Thrie beam Type Steel crash Barrier
 Thrie-Beare type steel barrier design is costlier than the simple W beam type crash barriers, but is less prone to damage by vehicle collisions, especially for shallow angle impacts .
The post and spacer blocks are of steel channel section 75 mm x 150 mm x 5 mm. 
The spacing of the posts is 2 met. centre to centre. The post is 850 mm above the ground and is driven into the ground to a length of 1150 mm. All the steel components and fasteners are galvanised by the hot dip process.

Question  22 -  What is the difference between CTB(CTSB) and GSB(Granular sub base) ?

Answer - 
CTB(CTSB) stands for cement treated sub-base while GSB stands for granular sub-base. 

1 - CTSB/CTB course are capable to carry more loads than granular sub base (GSB).

2  - CTSB/CTB performance is good in rutting and fatigue cracking as compared to GSB. 

3- CTSB/CTB gains strength as time passes even under traffic load but GSB does gain strength as time passes. 

4 - The thickness of CTB(CTSB) is significantly less than GSB layer for same traffic count because CTB (CTSB) has higher modulus. Hence Use of CTB, Reduce the aggregate quantity as compared to GSB.

5 - CTB has longer life as compared to GSB.
 
6 - CTB(CTSB) is best option in low lying water clogged area.

Mukesh Kumar 

Comments

  1. insurance ??? ?????? ?? ???? ??? ????? ??????? ????? ?? ???????? ???? ??? ?????? ?? ???, ??? ???? ??? ?? ?? ?? ???? ????? ?? ???? ???? ?? ???? ???

    ReplyDelete