Skip to main content

Surface finish and quality control of work [Tolerance of horizontal alignment (edge tolerance), surface level tolerance (Tolerance in Reduced level), surface regularities and irregularities, rectification (sub grade, GSB, WMM, DBM/BC, DLC, PQC) and riding quality of pavement ]


Surface finish and quality control of work:-

This article includes
Tolerance of horizontal alignment (edge tolerance), surface level tolerance (Tolerance in Reduced level), surface regularities and irregularities, rectification (sub grade, GSB, WMM, DBM/BC, DLC, PQC) and riding quality of pavement



A- Horizontally alignments

Horizontally alignments shall be reckoned w.r.t. the center line of the carriageway as shown on the drawings. The edge of the carriage way as constructed shall be correct within a tolerance of ±10 mm there from. The corresponding tolerance for edges of the roadway and lower layer of pavements shall be ±25 mm.


B- Surface Level 
The levels of the subgrade and different pavements courses as constructed, shall not vary from those calculated with reference to the longitudinal and cross-profile of the road shown on the drawing or as directed by the engineer beyond the tolerance mentioned in table below(table 900-1).
Provided, however, that the negative tolerance for wearing course shall not be permitted in conjunction with the positive tolerance for base course, if the thickness of the former is thereby reduced by more than the following limits-

4mm for bituminous wearing course of thickness 40 mm or more
3mm for bituminous wearing course of thickness less than 40 mm
5mm for concrete pavement slab.






For checking compliance with the above requirements for subgrade, sub-base and base course. Measurements of the surface levels shall be taken on a grid of points placed at 6.25 m longitudinally and 3.5 m transversely. For any 10 consecutive measurements taken longitudinally or transversely, not more than one measurement shall be permitted to exceed the tolerance as above, this one measurements being not excess of 5mm above the permitted tolerance.
For checking the compliance with the above requirements for bituminous wearing course and concrete pavements, Measurements of the surface levels shall be taken on a grid of points spaced at 6.25 m along the length and at 0.5 m from the edge and at the centre of the pavement. In any length of the pavement, compliance shall be deemed to be met for the final road surface, only if the tolerance given above is satisfied for any point on the surface.


C - Surface Regularity of pavement courses

The longitudinal profile shall be checked with a 3 metre long straight edge/moving straight- edge as directed by the engineer at the middle of each traffic lane along a line parallel to the centre line of the road.



The max. allowable difference b/w the road surface and underside of a 3 met.

Straight-edge when placed parallel with or right angles to the centre line of the road at points decided by the engineer shall be:-

For pavements surface (bituminous and cement concrete)                            3mm

For bituminous base course                                                                                   6mm

For GSB/base courses                             
                                                                                                                                      8mm

For sub-bases under concrete pavement.                                                          10mm

For subgrade                                                                                                            15mm


D - Rectification

Where the surface regularity of subgrade and the various pavements course fall outside the specified tolerance. The contractor shall be liable to rectify these in manner described below -

1-subgrade – it shall be rectify as constructed a new subgrade.

2- Granular sub-base - it shall be rectify as constructed a new sub-base.

3-WBM/WMM sub-base/base: it shall be rectify as constructed a new WBM/WMM. Only top 75mm shall be scarified and done. The area treated shall not be less than 5m long and 2m wide. In no case shall depressions be filled up  with  unmixed and ungraded material or fines. 

4- Bituminous construction: For bituminous construction other than wearing course, where the surface is low, the deficiency shall be corrected by adding fresh material over a suitable tack coat, if needed, and re-compacting as per specifications.

For wearing course, where the surface is high or low, the full depth of layer shall be removed and replaced with fresh material and compacted. In all cases where the removal and replacement of a bituminous layer is involved, the area treated shall not be less than 5m in length and not less than 3.5 m in width.

5-Dry lean concrete sub-base:  it shall be rectify as constructed a new DLC sub-base.the area treated shall be at least 3m long, not less than 1 lane width and extend to the full depth.

6-Cement concrete pavement: it may rectified by scrabbling or grinding using approved equipment. The areas which have been reduced in level shall be retextured in an approved manner either by cutting grooves (5mm deep) or roughening the surface by hacking the surface. If high areas in excess 6mm or low areas in excess of 3mm occur, and if the contractor cannot rectify, the slab shall be demolished and reconstructed at the contractor’s expense and in no case the area removed shall be less than the full width of the lane in which the irregularity occurs and full length of the slab.

E -Riding Quality:

The riding quality of bituminous concrete wearing surface, as measured  by a standard towed fifth wheel bump integrator(TFWBI- It is also known as Roughometer or Automatic Road Unevenness Recorder gives quantitative integrated evaluation of surface irregularities on an digital counter I LCD screen. It comprises of a single wheeled trailer, with a pneumatic tyre mounted on a chassis, on which an integrating device is fitted ), shall not more than 2000mm per Km.




Thanks a lot
Mukesh Kumar
Gyan of engineering 

Comments

Popular posts from this blog

Granular Sub-base Base (GSB) quantity / Compaction Factor value and / Loose thickness of GSB Layer

In this article we shall discuss three important points about granular sub base  (GSB) 1- How can we calculate the required GSB  quantity?  2 -  What is value of compaction factor for GSB? 3- How much loose thickness of GSB should be taken to get proper compacted layer thickness ?  1- How can we calculate the required GSB quantity? Let us consider Length of GSB bed (L) = 500 Met. Breadth of GSB bed (B) = 7 Met. Thickness of GSB Layer (T)  = 150 mm =0.150 Met. Max. Dry Density (MDD) =2.221 Gram/ Cubic Centimeter = 2221Kg/ Cubic metre Note  -  The value of MDD is calculated by conducting proctor density test as per IS 2720 (part -28) : 1983 (Reaffirmed - May 2015). Then Volume of GSB  Layer = ( Length of GSB Bed X Width of GSB Bed X Thickness of GSB Layer) Volume of GSB  Layer = L X B X T  Volume of GSB  Layer   = 500 X 7 X 0.150  Volume of GSB Layer    = 525 Cubic Metre We Know That Mass = Volume X Density in this case - Mass = Volume X MDD Putting

WMM(Wet Mix Macadam) quantity / Compaction Factor value for WMM / Loose thickness of WMM Layer

Wet Mix Macadam (WMM) quantity / Compaction Factor value for WMM / Loose thickness of WMM Layer  In this article we shall discuss three important points about wet Mix Macadam (WMM) 1- How can we calculate the required WMM  quantity?  2 -  What is value of compaction factor for WMM? 3- How much loose thickness should be taken to get proper compacted layer thickness ?  1- How can we calculate the required WMM quantity? Let us consider Length of WMM Bed(L) = 1 Km = 1000 Met. Breadth of WMM Bed(B)= 7 Met. Thickness of WMM Layer (T)  = 150 mm =0.150 Met. Max. Dry Density (MDD) =2.230 Gram/ Cubic Centimeter = 2230KG/ Cubic metre Note -  The value of MDD is calculated by conducting proctor density test as per IS 2720 (part -28) : 1983 (Reaffirmed - May 2015). Then Volume of WMM Layer = ( Length of WMM Bed X Width of WMM Bed X Thickness of WMM Layer) Volume of WMM Layer = L X B X T  Volume of WMM Layer   = 1000 X 7 X 0.150  Volume of WMM Layer    = 1050 C

Granular Sub base (GSB) specifications, GSB Grading, layer thickness, Water absorption, Physical requirements (like liquid limit, Plasticity index ,AIV), construction procedure or Rolling , measurement and treatment of GSB as per MORTH 5th revision and Indian standard in Civil engineering

Granular sub-base (GSB) SUB BASE (GSB)– The full form of GSB is granular sub base.it is being laid in road work because it plays two major roles 1- it works as  drainage layer 2- it provides a good sub base to laid base layer on it. How to calculate the quantity, compaction factor value and loose thickness of GSB? To know more information kindly visit on below link 🔗  Granular sub-base(GSB) Quantity,compaction factor and loose thickness Material –     The material to be used for the work shall be natural sand, crushed   gravel, crushed stone, crushed slag, or combination thereof depending upon the grading required use of material like brick metal, kankar and crushed concrete shall be permitted in the lower sub base. The material shall be free from organic or other deleterious constituents. Grading III and IV shall be used in lower sub base. Grading V and VI shall be used as sub-base-cum-drainage layer. Where the sub-base is laid in two layers as upper sub-base an

Dense Bituminous Macadam (DBM) or Bituminous Concrete (BC) layer Quantity / Compaction Factor value / Loose thickness calculation

Dense Bituminous  Macadam (DBM) or   Bituminous Concrete (BC)  quantity / Compaction Factor value for DBM or BC / Loose thickness of DBM or BC Layer  In this article we shall discuss three important points about Dense Bituminous   Macadam (DBM) or Bituminous Concrete (BC) 1- How can we calculate the required DBM/BC quantity?  2 -  What is value of compaction factor for DBM/BC? 3- How much loose thickness should be taken to get proper compacted layer thickness ?  1- How can we calculate the required DBM/BC quantity? Let us consider Length of  DBM/BC layer (L) = 1 Km = 1000 Met. Breadth of DBM/BC Layer (B)= 5 Met. Thickness of DBM/BC Layer (T)  = 50 mm =0.050 Met. Max. Dry Density (MDD) =2.441 Gram/ Cubic Centimeter = 2441KG/ Cubic metre Note  -  The value of MDD is calculated by conducting suitable test . Then Volume of DBM/BC Layer = ( Length of DBM/BC layer X Width of DBM/BC layer  X Thickness of DBM/BC Layer) Volume of DBM/BC Layer = L X B X T Volume o

Wet Mix Macadam (WMM) technical specifications as per MORTH and Indian standard in Civil engineering

WET MIX MACADAM (WMM) sub – base /base:- Wet mix macadam (WMM) act as a base course just below the bituminous layer (bitumen base course or surface course).  The thickness of a single compacted Wet mix macadam(WMM)  layer shall not be less than 75mm.when vibrating or other approved types of compacting equipment are used, the compacted depth of a single layer of the sub-base course may be up to 200mm. How to calculate the loose thickness of WMM, compaction factor and quantity of WMM ? Kindly visit on below link 🔗 WMM- loose thickness,quantity and compaction factor Physical requirements   Material finer than 425 micron shall have plasticity index (PI) not exceeding 6. To determine this combined portion, the flaky stone from a representative sample should first be separated out. Flakiness index is weight of flaky stone metal divided by weight of stone sample. Only the elongated particles are separated out from the remaining (non-flaky) stone metal. E

DBM (Dense Bituminous Macadam) specificatins,layer thickness, physical requirements, aggregate size, grades and its measurements

 DENSE BITUMINOUS MACADAM(DBM) DBM acts as a bituminous  base course and thickness of a single compacted  layer shall be 50 mm to 100 mm.  In this article we shall discuss about Technical specifications of DBM (Dense Bituminous Macadam), layer thickness, physical requirements, aggregate size, grades and its measurements A-Scope : The work shall consist of construction in a single layer of DBM on a previously prepared base or sub-base. The thickness of a single layer shall be 50 mm to 100 mm. B - Material : The choice of binder material shall be stipulated in the contract or by the engineer, where viscosity grades of bitumen are specified, they are referred to by a designation in accordance with IS: 73. Where modified bitumen is specified, it shall conform to the requirements of IRC:SP:53 and IS:15462. Selection criteria for viscosity grade bitumen based on highest and lowest daily mean temperatures at a particular site are ]given in table no -1. 1-Coarse Agg

Full form of various terms used in civil engineering /highway engineering or road work

Full Form of various  terms used in civil engineering  (Highway and expressway)  List of various  acronyms or abbreviations used in civil engineering  TBM- Temporary Bench mark (टे᠎म्‌प्‌ररि बेंच मार्क) BM- Bench Mark ( बेंच मार्क ) / Bituminous Macadam ( बिटुमिनस मैकडम) MSL- Mean Sea Level (मीन सी लेवल) BS- Back sight( बैक साइट) FS - Fore sight  (फोर साइट) HI - Height of Instrument ( हाइट आंफ इन्‌स्‍ट्रमन्‍ट्‌) TS-  Total Station (टोटल स्टेशन) GPS- Global Positioning System (ग्लोबल पोजिशनिंग सिस्टम) DGPS - Differential Global Positioning System ( डिफरेंसिअल ग्लोबल पोजिशनिंग सिस्टम) ROW- Right of Way (राइट ऑफ वे) MTV- material Transport vehicle (मटेरियल ट्रांसपोर्ट वहीकल) NGL- Natural Ground Level (नेचुरल ग्राउन्‍ड्‌ लेवल ) OGL- Original Ground level (अˈरिजन्‌ल्‌ ग्राउन्‍ड्‌ लेवल ) C&G- Clearing and Grubbing ( क्लियरिंग और ग्रबिंग) EMB- Embankment SG- Subgrade (सबग्रेड) GSB- Granular sub-base WMM- Wet Mix Macadam ( वेट मिक्स मैकडैम) WBM- Water Bound Ma

Difference between nominal mix and design mix of concrete

Difference between nominal mix and design mix of concrete - Concrete is most extensively used mix to achieve desired properties of structure. There are two methods to prepare the concrete mix. 1-Nominal mix 2- Design mix Nominal mix - Nominal mix specifies the fix proportion of the cement , sand and aggregates. Ingredients of concrete are mixed on the basis of volume. It is a site level mixing of ingredients to prepare concrete mix. Such type of concrete mix is generally used in small quantity or where load is not high. There are many grade of nominal mix concrete like M-5, M-7.5, M-10, M-15 and M-20. In above grades of concrete mix  the letter 'M' refers to Mix where as the value like 5,7.5,10,15 etc indicates the compressive characteristic strength of concrete after 28 days in specified conditios. Unit of this compressive characteristic strength of concrete is  Newton /mm 2. The ratio of various grade of concrete is being given below - M-5 

Bituminous Concrete (BC) specifications viz. Layer thickness, Mix and material requirements, grading , laying trials, Rolling , Construction procedure, transport and joint specifications, surface finish and quality control,measurement and rate etc..as per MORTH and Indian Standard

Bituminous concrete(BC)- Bituminous concrete( BC) is used for wearing  course and profile corrective courses.BC is generally laid in single layer on a previously prepared bituminous bound  surface. The thickness of single layer of BC shall be 30mm,40mm and 50mm. 1 -MATERIAL A- Bitumen - The bitumen shall be viscosity graded paving bitumin complying with IS 73 or specified in contract aggrement. The type and grade of bitumen to be used would depend upon the climatic condition and the traffic. Selection criteria of viscosity graded (VG) paving bitumens based on climatic conditions B- Coarse Aggregate It consist of crushed rock,crushed gravel or other hard material retained on 2.36 mm sieve. It shall be clean ,hard,durable and of cubical shape,free from dust,and  soft organic and other deleterious substances. The aggregates  shall satisfy the physical requirements of table  no. -2 (Table no. 500-16 ,as per MORTH 5th revision) where crushed gravel is proposed 

Civil engineering interview questions in Roadway/Highway /Expressway department

  Welcome friends, We shall learn about the various questions which are frequently ask by an  interviewer In the field of infrastructure.  So let's get start....... EMBANKMENT/SUBGRADE/BORROW AREA •Liquid Limit  <50% •Plastic Limit  < 25% •Proctor Density(Min. Value) For Embankment =1.52 to 1.60 gram/cubic centimeter For Subgrade= 1.75 gram/ cubic centimeter Sub-grade top • Field Dry Density (FDD) For Embankment= min. 95% For Sub grade = min. 97% •Number of test For Embankment = 1set/3000 sq.meter(1set=10pits) For subgrade= 1set/2000 sq.meter (1 set=10 pits) GRANULAR SUB- BASE •Maximum thickness of single compacted layer = 200 mm • Minimum thickness of single compacted layer( only when GSB is laying in two layers) = 150 mm •Max. Allowable size of aggregate =75mm •Number of grading of GSB = 6 •Liquid limit  should not be  more than 25% ( test procedure as per IS 2720 (part 5)). •Plasticity index should  not be more than 6%