Skip to main content

Cement treated soil and cement flyash treated sub-base /base (CTSB)[Detailed specifications and it's tolerance limits]

Cement treated sub-base (CTSB) / cement treated base (CTB) acts as a base course or sub base course depends upon purpose of use. CTSB/CTB course are capable to carry more loads than granular sub base (GSB).
CTSB/CTB performance is good in rutting and fatigue cracking as compared to GSB. When we compare CTSB/CTB courses with GSB course, CTSB/CTB gains strength as time passes even under traffic load. 

So to get detailed information, let's begin...............

1-Scope

This work shall consist of laying and compacting a sub-base/base course of soil treated with cement or cement-flyash on prepared subgrade/sub-base, in accordance with the requirements of these Specifications and in conformity with the lines, grades and cross-sections shown on the drawings or as directed by the Engineer.

To get the more technical specifications about granular sub base (GSB),kindly click on below link 🔗 



2-Materials

(I) Material to be Treated
The material used for cement or cement-flyash treatment shall be soil including sand and gravel, laterite, kankar, brick aggregate, crushed rock or slag or any combination of these. For use in a sub-base course, the material shall have a grading shown in Table -1. It shall have a uniformity coefficient not less than 5, capable of producing a well-closed surface finish. For use in a base course, the material shall be sufficiently well graded to ensure a well-closed surface finish and have a grading within the range given in Table -1. If the material passing 425 micron sieve is plastic, it shall have a liquid limit not greater than 45 percent and a plasticity index not greater than 20 percent determined in accordance with IS:2720 (Part 5).


(II) Physical requirements

If the water absorption of the aggregates determined as per IS: 2386(part-3) is greater than 2 %, the aggregates shall be tested for wet aggregate impact value (AIV) (IS: 5640). Soft aggregates like kankar, brick ballast and laterite shall also be tested for wet AIV.


(III) Cement

Cement for stabilization shall either be ordinary Portland Cement, Portland Slag Cement or Portland Puzzolana Cement and shall comply with the requirements of IS:269, 455 or 1489 respectively.

                       Table -1: Grading Limits of Material for Stabilisation with Cement

(IV) Lime
If needed for pre-treatment of highly clayey soils, the following treatment shall apply.
Lime for lime-soil stabilization work shall be commercial dry lime slaked at site or pre-slaked lime delivered to the site in suitable packing. Unless otherwise permitted by the Engineer, the lime shall have.purity of not less than 70 percent by weight of Quick-lime (CaO) when tested in accordance with IS:1514. Lime shall be properly stored to avoid prolonged exposure to the atmosphere and consequent carbonation which would reduce its binding properties.


(v) - Flyash
 Flyash may be from anthracitic coal or lignitic coal. Flyash to be used for cement-flyash treatment shall conform to the requirement given in Table- 2 and table -3.
                                        Table -2 Chemical requirements for fly ash as pozzolana


                                                  Table -3 Physical requirements for fly ash as a pozzolana

Pond ash or bottom ash, which do not meet the requirements of Tables -2 and table-3 can also be used for cement-flyash treatment. However, in all cases of cement stabilised fly-ash/ bottom ash/ pond ash, mix should develop adequate strength.

(VI) Quantity of Cement in Cement soil stabilised mix

The quantity of cement to be added as percent by weight of the dry soil shall be specified in the Contract. Also if lime is used as pretreatment for highly clayey soils, the quantity as percent by weight of dry soil shall be specified in the Contract. The mix design shall be done on the basis of 7 day unconfined compressive strength (UCS) and/or durability test under 12 cycles of wet-dry conditions. The laboratory strength values shall be at least 1.5 times the minimum field UCS value stipulated in the Contract.


(VII) Quantity of Cement in Cement/Fly Ash Treated Sub-base/Base
The quantity of cement shall be more than 2 percent by weight of cement/ fly-ash mix. The mix design shall be done to achieve a strength of 1.75 MPa when tested on cylindrical specimens compacted to the density at optimum moisture content, tested in accordance with IS:2720 (Part 8 as specified in the contract) after 7 days moist curing. The design mix shall indicate the proportions of cement and fly ash and the quantity of water to be mixed.

(VIII) Water

The water to be used for cement stabilization shall be clean and free from injurious substances. Potable water shall be used.

3- Construction Operations

(I) Weather Limitations

Stabilisation shall not be done when the air temperature in the shade is less than 10°C.

(II) Degree of Pulverisation

For stabilisation, the soil before addition of cement shall be pulverised, where necessary, to the extent that it passes the requirements as set out in Table -4 when tested in accordance with the appropriate  method.
                                            Table - 4 soil pulverisation requirements for cement stabilisation

(III) Clauses (α),(β) and (Φ) shall apply as regards spreading and mixing the stabilizer except that cement or lime plus cement as the case may be, shall be used as the stabilizing material in place of lime.

(α) Equipment for Construction
Stabilised soil sub-bases shall be constructed by mix-in-place method of construction or as otherwise approved by the Engineer. Manual mixing shall be permitted only where the width of laying is not adequate for mechanical operations, as in small-sized jobs.
The equipment used for mix-in-place construction shall be a rotavator or similar approved equipment capable of pulverizing and mixing the soil with additive and water to specified degree to the full thickness of the layer being processed, and of achieving the desired degree of mixing and uniformity of the stabilized material. If so desired by the Engineer, trial runs with the equipment shall be carried out to establish its suitability for work.
The thickness of any layer to be stabilized shall be not less than 100 mm when compacted. The maximum thickness can be 200 mm, provided the plant used is accepted by the Engineer.

(β) Mix-in-place Method of Construction 
Before deploying the equipment, the soil after it is made free of undesirable vegetation or other deleterious matter shall be spread uniformly on the prepared subgrade in a quantity sufficient to achieve the desired compacted thickness of the stabilised layer. Where single-pass equipment is to be employed, the soil shall be lightly rolled as directed by the Engineer.

The equipment used shall either be of single-pass or multiple pass type. The mixers shall be equipped with an appropriate device for controlling the depth of processing and the mixing b laces shall be maintained or reset periodically so that the correct depth of mixing is obtained at al times.
With single-pass equipment the forward speed of the machine shall be so selected in relation to tl-e rotor speed that the required degree of mixing, pulverisation and depth of processing is obtained. In multiple-pass processing, the prepared sub-grade shall be pulverised to the required depth with successive passes of the equipment and the moisture content adjusted to be within prescribed limits mentioned hereinafter. The lime shall then be spread uniformly and mixing continued with successive passes until the required depth and uniformity of processing have been obtained.
The mixing equipment shall be so set that it cuts slightly into the edge of the adjoining lane processed previously so as to ensure that all the material forming a layer has been properly processed for the full width.

(Φ) Construction with Manual Means
Where manual mixing is permitted, the soil from borrow areas shall first be freed of all vegetation and other deleterious mater and placed on the prepared subgrade. The soil shall then be pulverized by means of crow-bars, pick axes or other means approved by the Engineer.
Water in requisite quantities may be sprinkled on the soil for aiding pulverisation. On the pulverized soil, the lime in requisite quantities shall be spread uniformly and mixed thoroughly by working with spades or other similar implements till the whole mass is uniform. After adjusting the moisture content to be within the limits mentioned later, the mixed material shall be leveled up to the required thickness so that it is ready to be rolled.

(IV) Moisture Content for Compaction
The moisture content at compaction checked vide IS:2720 (Part 2) shall not be less than the optimum moisture content corresponding to IS:2720 (Part 8) nor more than 2 percent above it.

(V) Rolling

Clause(€) shall apply except that care shall be taken to see that the compaction of cement stabilised material is completed within two hours of its mixing or such shorter period as nay be found necessary in dry weather.
Clause (€) Immediately after spreading, grading and levelling of the mixed material, compaction shall be carried out with approved equipment preceded by a few passes of lighter rollers if necessary.
Rolling shall commence at edges and progress towards the centre, except at super elevated portions or for carriageway with unidirectional cross-fall where it shall commence at the inner edge and progress towards the outer edge. During rolling, the surface shall be frequently checked for grade and crossfall (camber) and any irregularities corrected by loosening the material and removing/adding fresh material. Compaction shall continue until the density achieved is at least 98 percent of the maximum dry density for the material determined in accordance with IS:2720 (Part 8).


Care shall be taken to see that the compaction of lime stabilised material is completed within three hours of its mixing or such shorter period as may be found necessary in dry weather.
During rolling it shall be ensured that roller does not bear directly on hardened or partially hardened treated material previously laid other than what may be necessary for achieving the specified compaction at the joint. The final surface shall be well closed, free from movement under compaction planes, ridges, cracks or loose material. All loose or segregated or otherwise defective areas shall be made good to the full thickness of the layer and recompacted.

(VI) Curing
The sub-base/base course shall be suitably cured for 7 days. Subsequent pavement course shall be laid soon after to prevent the surface from drying out and becoming friable. No traffic of ary kind shall ply over the completed sub-base unless permitted by the Engineer.


4 -Surface Finish 

The surface finish of construction shall conform to the requirements of Clause given below.

A- Horizontally alignments

Horizontally alignments shall be reckoned w.r.t. the center line of the carriageway as shown on the drawings.kThe tolerance for edges of the roadway and lower layer of pavements shall be ±25 mm.

B- Surface Level 
The levels of the subgrade and different pavements courses as constructed, shall not vary from those calculated with reference to the longitudinal and cross-profile of the road shown on the drawing or as directed by the engineer beyond the tolerance mentioned in table below(table 900-1).



For checking compliance with the above requirements for subgrade and sub-base. Measurements of the surface levels shall be taken on a grid of points placed at 6.25 m  longitudinally and 3.5 m transversely. For any 10 consecutive measurements taken longitudinally or transversely, not more than one measurement shall be permitted to exceed the tolerance as above, this one measurements being not excess of 5mm above the permitted tolerance.



C - Surface Regularity of pavement courses

The longitudinal profile shall be checked with a 3 metre long straight edge/moving straight- edge as directed by the engineer at the middle of each traffic lane along a line parallel to the centre line of the road.



The max. allowable difference b/w the road surface and underside of a 3 met.

Straight-edge when placed parallel with or right angles to the centre line of the road at points decided by the engineer shall be:-


For GSB/base courses                           
                                                                                                                                      8mm

For sub-bases under concrete pavement.                                                          10mm

For subgrade                                                                                                            15mm

5-Strength and Quality Control
Control on the quality of materials
and works shall be exercised by the Engineer.
Cement treated soil sub-base/base and cement/fly ash treated sub-base/base shall be tested for the unconfined compressive strength (UCS) value at 7 days, actually obtained in-situ. In case of variation from the design UCS, in-situ value being on lower side, prior to proceeding with laying of base/surface course on it, the pavement design shall be reviewed for actual UCS value. The extra pavement thickness needed on account of lower UCS shall be constructed by the Contractor at his own cost.

6 -Arrangements for Traffic
During the period of construction, arrangements for traffic shall be provided and maintained as directed by the engineer.

7- Measurements for Payment 
Stabilised soil sub-base/base shall be measured as finished work in position in cubic metres.

8-Rate
The Contract unit rate for cement treated soil sub-base/base with pretreatment with lime if required and cement/fly ash treated sub-base/base shall be payment in full for carrying out required operations including full compensation for all components listed below .
i) making arrangements for traffic as directed by the engineer in charge ;

 ii) supplying all materials to be incorporated in the work including all royalties, fees, rents where applicable with all leads and lifts;

iii) all labour, tools, equipment and incidentals to complete the work to the Specifications;

 iv) carrying out the work in part widths of road where directed; and

v) carrying out the required tests for quality control.

Thanks a lot
Mukesh Kumar
www.gyanofcivilengineering.com

Comments

Popular posts from this blog

Granular Sub base (GSB) specifications, GSB Grading, layer thickness, Water absorption, Physical requirements (like liquid limit, Plasticity index ,AIV), construction procedure or Rolling , measurement and treatment of GSB as per MORTH 5th revision and Indian standard in Civil engineering

Granular sub-base (GSB) SUB BASE (GSB)– The full form of GSB is granular sub base.it is being laid in road work because it plays two major roles 1- it works as  drainage layer 2- it provides a good sub base to laid base layer on it. How to calculate the quantity, compaction factor value and loose thickness of GSB? To know more information kindly visit on below link 🔗  Granular sub-base(GSB) Quantity,compaction factor and loose thickness Material –     The material to be used for the work shall be natural sand, crushed   gravel, crushed stone, crushed slag, or combination thereof depending upon the grading required use of material like brick metal, kankar and crushed concrete shall be permitted in the lower sub base. The material shall be free from organic or other deleterious constituents. Grading III and IV shall be used in lower sub base. Grading V and VI shall be used as sub-base-cum-drainage layer. Where the sub-base is laid in two layers as upper sub-base an

WMM(Wet Mix Macadam) quantity / Compaction Factor value for WMM / Loose thickness of WMM Layer

Wet Mix Macadam (WMM) quantity / Compaction Factor value for WMM / Loose thickness of WMM Layer  In this article we shall discuss three important points about wet Mix Macadam (WMM) 1- How can we calculate the required WMM  quantity?  2 -  What is value of compaction factor for WMM? 3- How much loose thickness should be taken to get proper compacted layer thickness ?  1- How can we calculate the required WMM quantity? Let us consider Length of WMM Bed(L) = 1 Km = 1000 Met. Breadth of WMM Bed(B)= 7 Met. Thickness of WMM Layer (T)  = 150 mm =0.150 Met. Max. Dry Density (MDD) =2.230 Gram/ Cubic Centimeter = 2230KG/ Cubic metre Note -  The value of MDD is calculated by conducting proctor density test as per IS 2720 (part -28) : 1983 (Reaffirmed - May 2015). Then Volume of WMM Layer = ( Length of WMM Bed X Width of WMM Bed X Thickness of WMM Layer) Volume of WMM Layer = L X B X T  Volume of WMM Layer   = 1000 X 7 X 0.150  Volume of WMM Layer    = 1050 C

Granular Sub-base Base (GSB) quantity / Compaction Factor value and / Loose thickness of GSB Layer

In this article we shall discuss three important points about granular sub base  (GSB) 1- How can we calculate the required GSB  quantity?  2 -  What is value of compaction factor for GSB? 3- How much loose thickness of GSB should be taken to get proper compacted layer thickness ?  1- How can we calculate the required GSB quantity? Let us consider Length of GSB bed (L) = 500 Met. Breadth of GSB bed (B) = 7 Met. Thickness of GSB Layer (T)  = 150 mm =0.150 Met. Max. Dry Density (MDD) =2.221 Gram/ Cubic Centimeter = 2221Kg/ Cubic metre Note  -  The value of MDD is calculated by conducting proctor density test as per IS 2720 (part -28) : 1983 (Reaffirmed - May 2015). Then Volume of GSB  Layer = ( Length of GSB Bed X Width of GSB Bed X Thickness of GSB Layer) Volume of GSB  Layer = L X B X T  Volume of GSB  Layer   = 500 X 7 X 0.150  Volume of GSB Layer    = 525 Cubic Metre We Know That Mass = Volume X Density in this case - Mass = Volume X MDD Putting

Wet Mix Macadam (WMM) technical specifications as per MORTH and Indian standard in Civil engineering

WET MIX MACADAM (WMM) sub – base /base:- Wet mix macadam (WMM) act as a base course just below the bituminous layer (bitumen base course or surface course).  The thickness of a single compacted Wet mix macadam(WMM)  layer shall not be less than 75mm.when vibrating or other approved types of compacting equipment are used, the compacted depth of a single layer of the sub-base course may be up to 200mm. How to calculate the loose thickness of WMM, compaction factor and quantity of WMM ? Kindly visit on below link 🔗 WMM- loose thickness,quantity and compaction factor Physical requirements   Material finer than 425 micron shall have plasticity index (PI) not exceeding 6. To determine this combined portion, the flaky stone from a representative sample should first be separated out. Flakiness index is weight of flaky stone metal divided by weight of stone sample. Only the elongated particles are separated out from the remaining (non-flaky) stone metal. E

Dense Bituminous Macadam (DBM) or Bituminous Concrete (BC) layer Quantity / Compaction Factor value / Loose thickness calculation

Dense Bituminous  Macadam (DBM) or   Bituminous Concrete (BC)  quantity / Compaction Factor value for DBM or BC / Loose thickness of DBM or BC Layer  In this article we shall discuss three important points about Dense Bituminous   Macadam (DBM) or Bituminous Concrete (BC) 1- How can we calculate the required DBM/BC quantity?  2 -  What is value of compaction factor for DBM/BC? 3- How much loose thickness should be taken to get proper compacted layer thickness ?  1- How can we calculate the required DBM/BC quantity? Let us consider Length of  DBM/BC layer (L) = 1 Km = 1000 Met. Breadth of DBM/BC Layer (B)= 5 Met. Thickness of DBM/BC Layer (T)  = 50 mm =0.050 Met. Max. Dry Density (MDD) =2.441 Gram/ Cubic Centimeter = 2441KG/ Cubic metre Note  -  The value of MDD is calculated by conducting suitable test . Then Volume of DBM/BC Layer = ( Length of DBM/BC layer X Width of DBM/BC layer  X Thickness of DBM/BC Layer) Volume of DBM/BC Layer = L X B X T Volume o

Full form of various terms used in civil engineering /highway engineering or road work

Full Form of various  terms used in civil engineering  (Highway and expressway)  List of various  acronyms or abbreviations used in civil engineering  TBM- Temporary Bench mark (टे᠎म्‌प्‌ररि बेंच मार्क) BM- Bench Mark ( बेंच मार्क ) / Bituminous Macadam ( बिटुमिनस मैकडम) MSL- Mean Sea Level (मीन सी लेवल) BS- Back sight( बैक साइट) FS - Fore sight  (फोर साइट) HI - Height of Instrument ( हाइट आंफ इन्‌स्‍ट्रमन्‍ट्‌) TS-  Total Station (टोटल स्टेशन) GPS- Global Positioning System (ग्लोबल पोजिशनिंग सिस्टम) DGPS - Differential Global Positioning System ( डिफरेंसिअल ग्लोबल पोजिशनिंग सिस्टम) ROW- Right of Way (राइट ऑफ वे) MTV- material Transport vehicle (मटेरियल ट्रांसपोर्ट वहीकल) NGL- Natural Ground Level (नेचुरल ग्राउन्‍ड्‌ लेवल ) OGL- Original Ground level (अˈरिजन्‌ल्‌ ग्राउन्‍ड्‌ लेवल ) C&G- Clearing and Grubbing ( क्लियरिंग और ग्रबिंग) EMB- Embankment SG- Subgrade (सबग्रेड) GSB- Granular sub-base WMM- Wet Mix Macadam ( वेट मिक्स मैकडैम) WBM- Water Bound Ma

DBM (Dense Bituminous Macadam) specificatins,layer thickness, physical requirements, aggregate size, grades and its measurements

 DENSE BITUMINOUS MACADAM(DBM) DBM acts as a bituminous  base course and thickness of a single compacted  layer shall be 50 mm to 100 mm.  In this article we shall discuss about Technical specifications of DBM (Dense Bituminous Macadam), layer thickness, physical requirements, aggregate size, grades and its measurements A-Scope : The work shall consist of construction in a single layer of DBM on a previously prepared base or sub-base. The thickness of a single layer shall be 50 mm to 100 mm. B - Material : The choice of binder material shall be stipulated in the contract or by the engineer, where viscosity grades of bitumen are specified, they are referred to by a designation in accordance with IS: 73. Where modified bitumen is specified, it shall conform to the requirements of IRC:SP:53 and IS:15462. Selection criteria for viscosity grade bitumen based on highest and lowest daily mean temperatures at a particular site are ]given in table no -1. 1-Coarse Agg

Difference between nominal mix and design mix of concrete

Difference between nominal mix and design mix of concrete - Concrete is most extensively used mix to achieve desired properties of structure. There are two methods to prepare the concrete mix. 1-Nominal mix 2- Design mix Nominal mix - Nominal mix specifies the fix proportion of the cement , sand and aggregates. Ingredients of concrete are mixed on the basis of volume. It is a site level mixing of ingredients to prepare concrete mix. Such type of concrete mix is generally used in small quantity or where load is not high. There are many grade of nominal mix concrete like M-5, M-7.5, M-10, M-15 and M-20. In above grades of concrete mix  the letter 'M' refers to Mix where as the value like 5,7.5,10,15 etc indicates the compressive characteristic strength of concrete after 28 days in specified conditios. Unit of this compressive characteristic strength of concrete is  Newton /mm 2. The ratio of various grade of concrete is being given below - M-5 

Bituminous Concrete (BC) specifications viz. Layer thickness, Mix and material requirements, grading , laying trials, Rolling , Construction procedure, transport and joint specifications, surface finish and quality control,measurement and rate etc..as per MORTH and Indian Standard

Bituminous concrete(BC)- Bituminous concrete( BC) is used for wearing  course and profile corrective courses.BC is generally laid in single layer on a previously prepared bituminous bound  surface. The thickness of single layer of BC shall be 30mm,40mm and 50mm. 1 -MATERIAL A- Bitumen - The bitumen shall be viscosity graded paving bitumin complying with IS 73 or specified in contract aggrement. The type and grade of bitumen to be used would depend upon the climatic condition and the traffic. Selection criteria of viscosity graded (VG) paving bitumens based on climatic conditions B- Coarse Aggregate It consist of crushed rock,crushed gravel or other hard material retained on 2.36 mm sieve. It shall be clean ,hard,durable and of cubical shape,free from dust,and  soft organic and other deleterious substances. The aggregates  shall satisfy the physical requirements of table  no. -2 (Table no. 500-16 ,as per MORTH 5th revision) where crushed gravel is proposed 

Civil engineering interview questions in Roadway/Highway /Expressway department

  Welcome friends, We shall learn about the various questions which are frequently ask by an  interviewer In the field of infrastructure.  So let's get start....... EMBANKMENT/SUBGRADE/BORROW AREA •Liquid Limit  <50% •Plastic Limit  < 25% •Proctor Density(Min. Value) For Embankment =1.52 to 1.60 gram/cubic centimeter For Subgrade= 1.75 gram/ cubic centimeter Sub-grade top • Field Dry Density (FDD) For Embankment= min. 95% For Sub grade = min. 97% •Number of test For Embankment = 1set/3000 sq.meter(1set=10pits) For subgrade= 1set/2000 sq.meter (1 set=10 pits) GRANULAR SUB- BASE •Maximum thickness of single compacted layer = 200 mm • Minimum thickness of single compacted layer( only when GSB is laying in two layers) = 150 mm •Max. Allowable size of aggregate =75mm •Number of grading of GSB = 6 •Liquid limit  should not be  more than 25% ( test procedure as per IS 2720 (part 5)). •Plasticity index should  not be more than 6%